AROUND 25,000 tonnes of earth and other material will be moved and backfilled with stone sourced from a nearby quarry – reopening a long-closed section of hard shoulder on the M4.

Contractors MJ Church will install 19,500 tonnes of stone to restore the embankment and hard shoulder as part of a scheme between junctions 16 (Swindon West, Royal Wootton Bassett) and 17 (Chippenham), which will also see the refurbishment of four bridges across the motorway.

Chris Hilldrup, National Highways route manager, said: “Many of the roads and bridges we manage were built around 60 years ago and are nearing the end of their life span, so we’re acting now and renewing them to prevent bigger problems further down the line.

“This £20 million investment along the M4 in Wiltshire is a significant engineering undertaking.

“Once we have stabilised the embankment, we will refurbish the bridges and upgrade barriers to maintain the safety and reliability of this busy route for many years to come.”

The landslide was identified during routine surveys and rendered the hard shoulder unsafe and unusable on the eastbound approach to Swindon.

The verges and embankments need to be stabilised before work starts on the bridge repairs in autumn next year.

To enable the first phase of work, the westbound carriageway between junctions 16 and 17 will be subject to overnight lane closures this month, with some overnight eastbound lane closures, and a daytime hard lane shoulder closure for vegetation and utilities work.

Ahead of the stabilisation work, full westbound overnight closures will be in place between 8pm and 6am on November 12 and 13 to install traffic management.

Two lanes will then be in place with a 50mph speed restriction until February 17, while the eastbound carriageway will continue as normal.

During the two overnight closures, HGVs will be diverted via Cirencester and Malmesbury, with other vehicles using separate diversion routes.

To minimise disruption, there will be lanes running in each direction for the first phase, which will only add an extra two minutes to people’s journey times, National Highways said.

Once the stabilisation work has been completed, National Highways will set about restoring the four bridges and the upgrade of 1.3 miles of safety barrier, with a programme of work scheduled from autumn 2027 to spring 2028.

The bridges carry the M4 over roads at Brinkworth and Grittenham, the Swindon to Bristol railway line and a farm access road.

Mr Hilldrup added: “We’re doing everything we can to minimise disruption, by keeping lanes running in each direction for the first phase, which will only add an extra two minutes to people’s journey times.

“We appreciate roadworks can impact on people’s journeys, and in the meantime, we advise people to plan ahead and allow extra time for their journeys through the works.”